Railway Recruitment Board Mathematics — Question 1716
Question
A is twice as good a workman as B, and together they finish a piece of work in 18 days. In how many days can B alone finish it?
- 18
- 54
- 36
- 27
Correct answer
B — 54
Explanation (English)
Let B's rate = 1 unit/day, so A's = 2 units/day; together 3 units/day. Total work = 3 × 18 = 54 units. B alone = 54/1 = 54 days.
More Mathematics questions
- Percentage — Due to 25 % reduction in the price of wheat per kg, John is able to buy 5 kg more for ₹600. What is the original price of wheat per kg?
- Ratio and Proportion — If the ratio of two numbers is 3:5 and their sum is 80, find the larger number.
- Time and Work — A can complete work in 12 days, B in 15 days. Together they finish in how many days?
- Mensuration — The area of a square is 144 sq.m. Find its perimeter.
- Number System — The sum of three consecutive odd numbers is 63. Find the largest number.
- Algebra — If x^2y^2 + 1/(x^2y^2) = 83, then the value of xy - 1/(xy) is :
Practice 1000+ more questions like this
TestPod AI has hand-curated previous-year-questions for SSC, RRB NTPC, IBPS PO, SBI Clerk, and more — with AI explanations in Tanglish, Hinglish, and English.