Question

A can complete a piece of work in 12 days and B in 15 days. Working together, in how many days will they finish it?

  1. 6 days
  2. 6 2/3 days
  3. 7 days
  4. 7 1/2 days

Correct answer

B — 6 2/3 days

Explanation (English)

Combined one-day work = 1/12 + 1/15 = 5/60 + 4/60 = 9/60 = 3/20. Time = 20/3 = 6 2/3 days.