Banking Exams Quant — Question 1803
Question
15 men can complete a work in 20 days. How many men are needed to complete the same work in 12 days?
- 30 men
- 22 men
- 25 men
- 20 men
Correct answer
C — 25 men
Explanation (English)
Total work = 15 × 20 = 300 man-days. Men needed for 12 days = 300 / 12 = 25 men.
More Quant questions
- Mixtures — In what ratio must rice at ₹24 per kg be mixed with rice at ₹60 per kg so that the mixture is worth ₹32 per kg?
- Simple Interest — A sum of money doubles in 8 years at simple interest. In how many years will it triple?
- Approximation — What approximate value should come in place of the question mark (?)? 24.97% of 640.12 + 18.03 × 11.98 − 143.9 ÷ 6.02 = ?
- Approximation — What approximate value should come in place of the question mark (?)? √1023.8 × 7.02 + 3.98³ − 299.91 ÷ 12.03 = ?
- Simplification — Find the value of ? in the following equation: (3/8 of 1440 + 45% of 680) ÷ 9 + ?² = 238
- Approximation — What approximate value should come in place of the question mark (?)? 39.98% of 1249.89 − ? = 16.02² − 7.99 × 11.03
Practice 1000+ more questions like this
TestPod AI has hand-curated previous-year-questions for SSC, RRB NTPC, IBPS PO, SBI Clerk, and more — with AI explanations in Tanglish, Hinglish, and English.