Staff Selection Commission Quantitative Aptitude — Question 1982

Question

12 men or 18 women can complete a piece of work in 14 days. In how many days will 8 men and 16 women together complete the same work?

  1. 9 days
  2. 12 days
  3. 10 days
  4. 8 days

Correct answer

A — 9 days

Explanation (English)

1 man = 1.5 women, so 8 men + 16 women = 28 women; work = 18 × 14 = 252 woman-days, giving 252/28 = 9 days.