Railway Recruitment Board Mathematics — Question 2315

Question

A can complete a work in 20 days and B in 30 days. They start together, but A leaves 5 days before the work is completed. In how many days is the work completed?

  1. 12 days
  2. 15 days
  3. 14 days
  4. 17 days

Correct answer

B — 15 days

Explanation (English)

B works all T days and A works (T − 5) days: (T − 5)/20 + T/30 = 1 ⇒ 5T = 75 ⇒ T = 15 days.