Railway Recruitment Board Mathematics — Question 2586

Question

A and B can complete a piece of work in 15 days and 20 days respectively. They work together for 4 days and then A leaves. In how many more days will B alone finish the remaining work?

  1. 12 days
  2. 8 days
  3. 11⅓ days
  4. 10⅔ days

Correct answer

D — 10⅔ days

Explanation (English)

Total work = LCM(15, 20) = 60 units; A = 4, B = 3 units/day. In 4 days they do 28 units, leaving 32. B needs 32/3 = 10⅔ days.