A is 50% more efficient than B. In one day, C does half as much work as A and B together do. If C alone can finish a piece of work in 40 days, in how many days can A, B and C together finish it?
- 12 days
- 13 1/3 days
- 15 days
- 16 2/3 days
Correct answer
B — 13 1/3 days
Explanation (English)
Let B = 2 units/day, A = 3, C = (3 + 2)/2 = 2.5. Work = 2.5 × 40 = 100 units. Together = 7.5 units/day, so 100 ÷ 7.5 = 13 1/3 days.
More Quant questions
- Mixtures — In what ratio must rice at ₹24 per kg be mixed with rice at ₹60 per kg so that the mixture is worth ₹32 per kg?
- Simple Interest — A sum of money doubles in 8 years at simple interest. In how many years will it triple?
- Approximation — What approximate value should come in place of the question mark (?)? 24.97% of 640.12 + 18.03 × 11.98 − 143.9 ÷ 6.02 = ?
- Approximation — What approximate value should come in place of the question mark (?)? √1023.8 × 7.02 + 3.98³ − 299.91 ÷ 12.03 = ?
- Simplification — Find the value of ? in the following equation: (3/8 of 1440 + 45% of 680) ÷ 9 + ?² = 238
- Approximation — What approximate value should come in place of the question mark (?)? 39.98% of 1249.89 − ? = 16.02² − 7.99 × 11.03
Practice 1000+ more questions like this
TestPod AI has hand-curated previous-year-questions for SSC, RRB NTPC, IBPS PO, SBI Clerk, and more — with AI explanations in Tanglish, Hinglish, and English.