Railway Recruitment Board Mathematics — Question 2991

Question

Anil and Balbeer can finish a task in 3 days. They started working together, but after 2 days Anil got injured. Balbeer took 2 more days to finish the task. In how many days can Balbeer alone finish the same task?

  1. 5
  2. 9
  3. 10
  4. 6

Correct answer

D — 6

Explanation (English)

Together they finish 2/3 in 2 days; Balbeer alone does the remaining 1/3 in 2 days, so he needs 6 days for the whole task.