Railway Recruitment Board Mathematics — Question 3055

Question

A can complete 25% of a task in 10 days. B can complete 40% of the task in 40 days and C can complete 1/3 of the task in 13 days. Who among them has the fastest speed to complete the same task?

  1. B
  2. A
  3. All have the same speed
  4. C

Correct answer

D — C

Explanation (English)

Full task takes A 40 days, B 100 days and C 39 days. C needs the fewest days, so C is fastest.