Railway Recruitment Board Mathematics — Question 3387
Question
A and B can do a piece of work in 9 days and 12 days, respectively. A starts the work and they work on alternate days. They can finish the work in:
- 11 1/4 days
- 11 days
- 10 1/4 days
- 10 2/7 days
Correct answer
C — 10 1/4 days
Explanation (English)
Take total work 36 units; A does 4 and B does 3 per day. Ten days give 35 units, and A needs 1/4 of the 11th day for the last unit, so 10 1/4 days.
More Mathematics questions
- Percentage — Due to 25 % reduction in the price of wheat per kg, John is able to buy 5 kg more for ₹600. What is the original price of wheat per kg?
- Ratio and Proportion — If the ratio of two numbers is 3:5 and their sum is 80, find the larger number.
- Time and Work — A can complete work in 12 days, B in 15 days. Together they finish in how many days?
- Mensuration — The area of a square is 144 sq.m. Find its perimeter.
- Number System — The sum of three consecutive odd numbers is 63. Find the largest number.
- Algebra — If x^2y^2 + 1/(x^2y^2) = 83, then the value of xy - 1/(xy) is :
Practice 1000+ more questions like this
TestPod AI has hand-curated previous-year-questions for SSC, RRB NTPC, IBPS PO, SBI Clerk, and more — with AI explanations in Tanglish, Hinglish, and English.