Question

A, B and C can complete a piece of work in 12, 20 and 15 days, respectively. A, B and C will complete the work while working on alternate days. C works on the 1st day, B works on the 2nd day and A works on the 3rd day and so on. In how many days will the work get complete?

  1. 24
  2. 15
  3. 30
  4. 12

Correct answer

B — 15

Explanation (English)

With 60 units, C,B,A do 4,3,5; a cycle of 3 days does 12, so 5 cycles = 15 days.