A, B and C working separately can do a piece of work in 5, 8 and 6 days, respectively. If they all work together and earn ₹22,774 for the whole work, then find the difference between the shares of B and C.

  1. ₹1,930
  2. ₹1,560
  3. ₹1,840
  4. ₹2,010

Correct answer

A — ₹1,930

Explanation (English)

Daily rates 24:15:20 (total 59); B and C differ by 5 parts = 5 x 386 = 1930.